Just received an email from my HA regarding the charger install requesting more documentation.
We now have a full list of what is needed from the customer post installation of an EVC:
Electrical Installation Certification (EIC) includes NICEIC/NAPIT electrical installation of full works โ you have provided thank you
Would you be able to provide the following please
EV charge point installation certificate along with make and model + clear photo of installation
Certification of Part P Building Control โ Ohme have advised this should have been sent out to you
Evidence from the District Network Operator (DNO) โ due to GDPR Ohme has said they cannot provide this and would need to come from the tenant – DNO (Northern power grid) gave approval on the 18th Dec, the approval reference is ENQ23160563.
Documentation on manufacturers warranties if receivedI don’t have any of the above, and no idea what they want from the DNO?
Please excuse spelling/typos. Apart from being a clot it turns out I had one on my cerebellum that's now causing various problems!