- This topic has 7 replies, 3 voices, and was last updated 1 week, 4 days ago by .
- Topic
I had my EV charger fitted 3 weeks ago. No issues with my property and a straight forward job according to the fitter from Pro EV. However I have just received an e-mail from SP energy networks on behalf of Pro EV who made an application for me. It says following an assessment to my property I require a cable head upgrade. Has anyone else had this? I imagine if it was a big job the EV charger wouldn’t have been fitted before this point? I find it strange none of this was carried out priory to the charger being fitted unless it is a small job. I have a driveway and recently got a rewire done.
Thanks!