Reply To: Everything Enyaq

#285288
Avatar photoSolymar
Participant

    Well, another week gone by & still in the dark! According to my contact at the Skoda dealership, the car should have gone into build 3 weeks ago! It’s not showing as built, there’s no chassis number and no other build week showing! So I’m not sure what’s going on and the dealership don’t seem to know!

    Surely there should be some visibility on the Skoda system, it can’t just dissappear,  can it?

    Skoda Enyaq Coupe 85x Sportline Plus Adanced, Heat Pump & 21" Supernova Wheels In Moon White Metallic - Ordered 27th December 2023 - Confirmed 31st January 2024 - Build Week 16 (W/C April 15th) Estimated Delivery 26th May. Build Week moved back to week 23 W/C 3rd June) Build Week moved again to week 32 (W/C 5th August) Brought forward to week 27 (W/C 1st July 24) Advised Week 31 That car us built & in Transit to UK. August 22nd, car arrived at dealership but wrong spec. Collected the car 18/9/2024. Ver