Reply To: DNO approval for domestic EV chargers

#297522
kezo
Participant

    In most cases you do not need approval from your DNO and its a simple case of connect & notify. The installer installs the charger and notify’s the relevant DNO within 28days however, you DNO won’t write to you, telling of the notification.

    Pod Point would have notified your DNO, so wouln’t worry too much mate.